Maine Locomotive & Machine Works cut out another large batch of boiler tubes over the last week. We added the tubes to our growing pile outside of the shop, clearing the way for more to be removed in the coming weeks. Check out how empty it's getting inside!
Work has also continued on the tender. The water outlet was drilled in the bottom of the tender tank (cistern) and all freshly cut edges on the new access panels have been ground down for safety. There is just a little more work to do before we coordinate with our crane operator to schedule the tender pick!
Present throughout the week were: Ron, Leverett, Hanna, Paul VS, Jim